BNSF charges city of Lincoln $50,000 for delaying trains 7.5 hours

(Source: Nebraska Watchdog, June 4, 2014)

LINCOLN, Neb. — When two girders slipped last year on a pedestrian bridge being built across railroad tracks to Lincoln’s new Pinnacle Bank Arena, the bridge failure delayed the bridge opening two months and racked up an extra $800,000 in repairs. Among the collateral damage was $50,000 the city had to pay BNSF Railway because train traffic below the bridge was delayed for 7.5 hours the day the $5 million bridge failed.

Full story: Nebraska Watchdog

Thursday, June 05, 2014

Like us on Facebook at

Sign up for BLET News Flash Alerts

© 1997-2016 Brotherhood of Locomotive Engineers and Trainmen


Decertification Helpline
(216) 694-0240

National Negotiations

Sign up for BLET
News Flash Alerts


Maryland governor pledges to revamp ‘infamous’ Howard Street Tunnel
Boston’s mayor joins TWU members to protest privatization plans
High-speed rail route to L.A. coming in to view
Negotiations with SEPTA workers stall as strike deadline nears
CN to report 3Q 2016 financials at 4 p.m. today
TPP would be another blow to U.S. manufacturing
Genesee & Wyoming acquires Australian railroad operation
Denver US Foods Teamsters launch unfair labor practice strike
Contractor can’t sue Union Pacific for amputation of legs
Deaf passenger’s lawsuit persists in 2012 Amtrak crash
The booming China-Europe rail network is taking the next step
Railroad retiree earnings limits to rise in 2017
Railroad Retirement benefits will increase in 2017
Get the latest labor news from the Teamsters

More Headlines